Do I need a permit to move a gas line or power line?
Yes, a permit from the City of Del Mar Building Department is required prior to relocating a gas or electrical line. However, first you must contact San Diego Gas and Electric (SDG&E) and obtain a work order from a SDG&E planner. Then visit the Planning Counter at Del Mar City Hall with the work order in hand. A City Planner will then ask you a few necessary questions and help you fill out the proper Letter of Authorization forms in order for the Building Department to accept and process your request for plumbing (gas) or electrical (power) permit. Please note that a City Encroachment Permit will also be required if any of the work would be located in the public right-of-way.