Jan. 25-26: All-night bluff work to cause significant noise disruptions near 9th Street
SANDAG is warning that round-the-clock work along the railway Jan. 25-26 will cause noise and parking restrictions on 9th Street.
A concrete pump to be positioned at the bottom of the street will generate considerable noise. So will the nonstop coming and going of concrete trucks starting at 4 a.m. Jan. 25 and continuing into the evening of Jan. 26.
No-parking restrictions are scheduled for both sides of 9th Street west of Stratford Court.
The work is part of SANDAG's Del Mar Bluffs Stabilization 5 project and will coincide with a full closure of the railway for passenger and freight trains.
Night work on the bluffs is expected to continue through mid-2027.
Open SANDAG construction notice
Open SANDAG Del Mar Bluffs Stabilization webpage
Contact SANDAG: 858-549-RAIL or LOSSANcorridor@SANDAG.org