Progress Report
September 6, 2019 ยท Issue No. 37
In this issue: Signs of the Times

sign installation

Signs of the Times

As the Downtown Streetscape Project approaches the finish line later this month, workers are completing punch list items such as replacing signs that were taken down during construction.

sign installation
sign installation
sign installation

Week of Sept. 9

  • 12th to 11th streets, west side: tree planting and irrigation installation;
  • Preparation for asphalt paving; and
  • Punch-list items. 

tree planting
One by one, trees are planted for the Downtown Streetscape Project.
irrigation installation
A worker glues a section of purple irrigation pipe.
Purple pipes fitted with "bubblers" provide water for Streetscape trees.
Purple pipes fitted with "bubblers" provide water for Streetscape trees.
Electrical workers pull wire for streetlights.
Electrical workers pull wire for streetlights.

Streetscape in a nutshell

The Downtown Streetscape Project will beautify Camino del Mar and improve safety between 9th and Plaza streets. The $8.1 million project includes new sidewalks, crosswalks, bike lanes, street furniture, landscaping, paving and other improvements. Construction is scheduled to run through September. The Downtown Streetscape Project was first envisioned in 1996 as part of a citywide street and sidewalk improvement program.

Streetscape video

Del Mar TV tells the story of the downtown beautification program with voices from City leaders and members of the project team. Watch the video.

Free parking at Civic Center

Visitors to downtown Del Mar can park for free at the Del Mar Civic Center, 1050 Camino Del Mar. The garage is accessible from entrances on 10th and 11th streets and by a stairway or elevator that connect to the plaza above.