Progress Report
June 28, 2019 ยท Issue No. 27
In this issue: Closures for Crosswalk Construction

1100 block reconstruction
11th Street just east of Camino del Mar is scheduled to reopen next week with new pavement, curbing and brick paver crosswalks.

For the Downtown Streetscape Project, a full closure of 11th Street just east of Camino del Mar is expected to remain in place until July 5 so crews can build brick paver crosswalks and pave the road.

Also next week, complete closures of 13
th and 12th streets just west of Camino del Mar are scheduled for Monday, Tuesday and Wednesday to build brick paver crosswalks at those locations.



Sidewalk on 1100 block
Extra-wide sidewalks are part of the new construction on the 1100 block of west Camino del Mar.

On the 1100 block, asphalt and concrete work

Concrete and asphalt work continued on the 1100 block this week with crews building curbs, gutters and sidewalks and paving the northern half of the block with fresh asphalt for angled parking. Also on the north end, at 12th Street, crews built a footing for a retaining wall. 

Throughout the project, electrical crews worked 12-hour days to finish installation of conduit in the Camino del Mar medians, among other tasks

Asphalt work on the 1100 block
The 1100 block makeover includes fresh asphalt for angled parking.
footing at 12th street
Workers build a footing for a retaining wall at 12th Street and Camino del Mar.
An architect's rendering of the 1100 block of Camino del Mar.
An architect's rendering of the 1100 block of Camino del Mar.

Week of July 1

Southbound Camino del Mar, 1100 block

  • Curb, gutter, sidewalk and retaining wall construction
  • Demolition
  • Silva cell installations for tree planting and stormwater capture

Southbound Camino del Mar at 13th and 12th streets

  • Brick paver crosswalk construction

Southbound Camino del Mar and medians, 11th to 9th streets

  • Electrical conduit and irrigation line installation 

Camino del Mar and medians, project-wide

  • Installation of valves, drip lines, flow meters and other irrigation equipment

July 16: "Rocky Road" ice cream social

We understand how disruptive construction can be. To thank residents and business owners for their patience, we are hosting a Rocky Road-themed ice cream social (PDF) from 3:30 to 5:30 p.m. July 16 at the Del Mar Civic Center, 1050 Camino del Mar. As the project reaches the home stretch, join us for a scoop as we show displays and answer your questions.


Streetscape in a nutshell

The Downtown Streetscape Project will beautify Camino del Mar and improve safety between 9th and Plaza streets. The $7.2 million project includes new sidewalks, crosswalks, bike lanes, street furniture, landscaping, paving and other improvements. Construction is scheduled to run through August. The Downtown Streetscape Project was first envisioned in 1996 as part of a citywide street and sidewalk improvement program.

July 8: Biweekly briefing, public welcome

Residents and business owners are invited to meet the project team and get the latest information on construction activity during biweekly briefings at the Del Mar Civic Center Town Hall, 1050 Camino del Mar. The next briefing is set for 9 a.m. Monday, July 8. 

Free parking at Civic Center

Visitors to downtown Del Mar can park for free at the Del Mar Civic Center, 1050 Camino Del Mar. The garage is accessible from entrances on 10th and 11th streets and by a stairway or elevator that connect to the plaza above.