Progress Report
March 15, 2019 ยท Issue No. 12
In this issue: The 1100 Block

bricklayers at 12th street
On the east side of Camino del Mar, construction activity is heavy along the 1100 block.

The 1100 Block

Downtown Streetscape construction this week continued to concentrate on the east side of the 1100 block of Camino del Mar. Since the project began in January, the 1100 block has represented the most involved block so far, with new construction stretching from storefronts to the highway. Crews have built curbs, sidewalks, brickwork and drainage.

More of the same is scheduled for the week ahead, including construction of a retaining wall and pedestrian ramp at the northeast corner of Camino del Mar and 11th Street. Work on the 1100 block is scheduled to continue through the week of March 25 to complete the pedestrian ramp and paving of parking spaces.

new sidewalk at 12th street
Hardscaping, landscaping and forest pansy trees are among the improvements shown in this rendering. 
fresh sidewalks in the 1100 block
Fresh sidewalks and brickwork.
1100 block parking
Newly-graded, angled parking will provide a smoother transition from northbound Camino del Mar.
1100 block Silva Cell
Silva Cells improve tree growth and capture stormwater runoff.

Week of March 18

In addition to continued construction on the 1100 block, crews are scheduled to begin vegetation clearing and demolition and to begin pouring sidewalks on the 1000 block. Demolition and sidewalk construction also is scheduled to begin on the 900 block.

Streetscape in a nutshell

The Downtown Streetscape Project will beautify Camino del Mar and improve safety between 9th and Plaza streets. The $6.8 million project includes new sidewalks, crosswalks, bike lanes, street furniture, landscaping, paving and other improvements. Construction is scheduled to run through June. The Downtown Streetscape Project was first envisioned in 1996 as part of a citywide street and sidewalk improvement program.


Monday: Biweekly briefing, public welcome

Residents and business owners are invited to meet the project team and get the latest information on construction activity during biweekly briefings at the Del Mar Civic Center Town Hall, 1050 Camino del Mar. The next briefing is set for 9 a.m. Monday, March 18. Download a schedule (PDF)

Free parking at Civic Center

Visitors to downtown Del Mar can park for free at the Del Mar Civic Center, 1050 Camino Del Mar. The garage is accessible from entrances on 10th and 11th streets and by a stairway or elevator that connect to the plaza above.

traffic control devices

Safety is no accident

In construction areas, one of two lanes and parallel parking will be closed during work hours. Sidewalks could be closed temporarily. Please read and follow all posted signs. Do not cross orange fencing and stay clear of closed sidewalks. Thank you!


Timeline