Progress Report
March 1, 2019 ยท Issue No. 10 
In this issue: Crosswalks

13 Street crosswalk
A worker installs concrete pavers at the 13th Street crosswalk.

Crosswalks taking shape

For a project designed to improve pedestrian safety, new and reconfigured crosswalks are a key component.

This week, workers set pavers for crosswalks on the east side of Camino del Mar at 14th, 13th and 12th streets.

The Downtown Streetscape Project on Camino del Mar will improve all crosswalks between 15th and 9th streets and add a brand new crosswalk, with pedestrian-activated flashing lights, across the highway at 10th Street.

Crosswalks at 13th and 11th streets will be expanded from 3- to 4-way crossings. All crosswalks will be built with 4-inch-by-12-inch concrete pavers in earth tones.

The installations require temporary lane closures.

12th Street crosswalk.
12th Street crosswalk.

Progress report

In addition to crosswalk installations, this week crews began building footings for streetlights  between Plaza and 13th streets. Next week, that work will continue between Plaza and 15th streets on the west side of Camino del Mar. Crosswalks will be extended across the inside lanes of northbound Camino del Mar at 14th, 13th and 12th streets.

Also for the week beginning March 4, construction activities will continue to concentrate on the east side of the 1100 block of Camino del Mar. 

Streetscape in a nutshell

The Downtown Streetscape Project will beautify Camino del Mar and improve safety between 9th and Plaza streets. The $6.8 million project includes new sidewalks, crosswalks, bike lanes, street furniture, landscaping, paving and other improvements. Construction is scheduled to run through June. The Downtown Streetscape Project was first envisioned in 1996 as part of a citywide street and sidewalk improvement program.


Monday: Biweekly briefing, public welcome

Residents and business owners are invited to meet the project team and get the latest information on construction activity during biweekly briefings at the Del Mar Civic Center Town Hall, 1050 Camino del Mar. The next briefing is set for 9 a.m. March 4. Download a schedule (PDF)

Free parking at Civic Center

Visitors to downtown Del Mar can park for free at the Del Mar Civic Center, 1050 Camino Del Mar. The garage is accessible from entrances on 10th and 11th streets and by a stairway or elevator that connect to the plaza above.

traffic control devices

Safety is no accident

In construction areas, one of two lanes and parallel parking will be closed during work hours. Sidewalks could be closed temporarily. Please read and follow all posted signs. Do not cross orange fencing and stay clear of closed sidewalks. Thank you!