2018 Streetscape Segment 5 Project

City Council approved a citywide sidewalk connectivity project to improve pedestrian access, bicycle safety, drainage and roadway paving along Camino Del Mar, Jimmy Durante Blvd and Via De La Valle on May 8, 2013. Segment 5 of the citywide plan refers to the section of Camino del Mar between Carmel Valley Road and 4th Street/Del Mar Heights Road. Segment 5 maintains two northbound lanes, one southbound lane, and the current free-right turn, from westbound Carmel Valley Road to northbound Camino del Mar. The project also includes additional parking spaces, a double left turn lane from Camino del Mar southbound to Del Mar Heights Road eastbound, and a new multi-purpose pathway on the west side of Camino del Mar. Medians and landscaping areas will be planted with drought tolerant vegetation, as presented to the Parks and Recreation Committee.

On March 5, 2018 City Council approved the award of the Segment 5 Construction Contract to Eagle Paving Company. Project construction scheduled for July 2018 completion.

CDM Segment 5 Project Map

**7/11/2018 STATUS UPDATE**

Traffic Signal Poles are schedule to be delivered and installed by the end on July.  Once installed, southbound traffic striping will be adjusted to allow two left turns on to Del Mar Heights Road, from southbound Camino del Mar.

Schedule

Median Work • April • Complete with exception of median nose, to be adjusted when new signal poles arrive.

West Side Demolition • April-May • Complete 

Install Storm Water Facilities • April-May • Complete

Construct New Sidewalks • April-May • Complete

Construct Intersection Camino Del Mar and Carmel Valley Road • May • Complete  

Grinding and Overlay Paving • May 23, 24 & 25 • Complete 

Installation of Shared Use Pathway from 4th Street to Carmel Valley Road • June • Complete as of 6/29/18

Install New Traffic Signal Poles • July • Poles scheduled for delivery and installation in late July. No Change.

Thermostriping • July •  Scheduled for 7/8/2018  In process, will be completed by 7-12-18

July 2018 Target Completion No change.